PA TURNPIKE MILEPOSTS 202-206 TOTAL RECONSTRUCTION AND WIDENING PROJECT

Construction Schedule

Preliminary Work: September 2016 to March 2017

Phase 1: March 2017 to December 2017

  • Work Zone Setup
  • Place construction barrier along the outside edge of existing Turnpike eastbound and westbound lanes
  • Excavate and install stormwater drainage
  • Construct new (third) westbound and eastbound lane and shoulders
  • Install concrete retaining walls on mainline near SR 997
  • Construct new mainline bridges over Mountain Road (SR 4007) and Bore Mill Run
  • Construct new SR 997 bridge over mainline
  • Build new SR 997, switch traffic onto new roadway, remove old SR 997

Phase 1 Traffic Impacts

  • Weekday mainline eastbound and westbound lane closures
  • 1 week detour of traffic on Enola Road for completion of new Enola Road tie-ins
  • Periodic traffic stoppage on Mountain Road (SR 4007)

Phase 2: December 2017 to December 2018

  • Shift mainline Turnpike to new outside lanes and shoulders
  • Remove median and excavate existing eastbound and westbound lanes
  • Install stormwater drainage
  • Construct new eastbound and westbound lanes and median
  • Reconstruct center sections of mainline bridges over Mountain Road (SR 4007) and Bore Mill Run
  • Install concrete median barrier/glare screen

Phase 2 Traffic Impacts

  • Weekday mainline eastbound and westbound lane closures
  • Periodic traffic stoppage on Mountain Road (SR 4007)