Turnpike Milepost A31-A38 Project

Construction Schedule and Staging

Stages 1 and 2 Construction: Early 2018 to Late 2019

  • Install advance signing (Stage 1)
  • Reconstruct existing northbound and southbound shoulders at northern end of the project (Stage 1)
  • Install right-of way fence and environmental controls
  • Install concrete construction barrier at outside edge of northbound and southbound right lane
  • Begin sound barrier construction
  • Excavate for and construct new northbound and southbound outside third lane and shoulder
  • Construct outside sections of new bridges over Schoolhouse Road, Creamery Road and Dietz Mill Road and Perkiomen Creek
  • Install stormwater drainage pipes and inlets
  • Construct drainage basins at ten locations

Stage 3 Construction: Late 2019 to Late 2020

  • Shift two lanes of northbound and two lanes of southbound traffic to the newly reconstructed northbound and southbound lane and shoulder
  • Remove existing northbound and southbound travel lanes
  • Install remaining stormwater drainage pipes and inlets
  • Complete construction of drainage basins
  • Complete sound barrier construction
  • Reconstruct the existing two northbound and southbound travel lanes
  • Replace middle section of bridges over Schoolhouse Road, Creamery Road, Dietz Mill Road and Perkiomen Creek

 