PA Turnpike / I-95 Interchange Project

Section A1 - Bridge Replacement at Bensalem Interchange Ramps over Mainline

Project Description

The Section A1 project involves the replacement of the two existing bridges at the Bensalem (Route 1) Interchange with a single span bridge.  The footprint of the proposed bridge is being shifted east to accommodate the new staged ramp configuration for the future widening of the PA Turnpike. Additionally the existing Westbound on ramp will be realigned to improve the current traffic flow operations.

The construction for this project also includes:

  • Demolition of existing bridges over PA Turnpike mainline.
  • Building of mechanically stabilized earth (MSE) wall adjacent to eastbound PA Turnpike mainline off-ramp.
  • Construction of future eastbound PA Turnpike mainline off-ramp roadway.
  • Placement of concrete pavement via staged ramp reconstruction.
  • Upgrade of drainage measures and mast lighting installed throughout the Interchange.
  • Installation of a precast slab interlocking system located at the Interchange’s roadway approach.

Project Schedule

The Notice To Proceed was August 2016. The duration of the project is over two and half (2 ½) years with construction completing by May 2019.

Construction Status

Project status is completed as of June 2020

Image Gallery

  • Placement of bedding material for precast pavement slabs
    (Mar/Jul 2019)

  • Drilling of load transfer bars for precast pavement slabs
    (Mar/Jul 2019)

  • Setting of precast pavement slab to adjacent slab
    (Mar/Jul 2019)

  • Hand grading prior to placement of precast pavement slab
    (Mar/Jul 2019)

  • Aligning of precast pavement slab in corner
    (Mar/Jul 2019)

  • Joining precast pavement slab with existing cast in place concrete slab
    (Mar/Jul 2019)

  • Completed precast pavement slabs
    (Mar/Jul 2019)

  • Excavation of sediment trap 3A
    (Mar/Jul 2019)

  • Slope stabilization of sediment trap 3B
    (Mar/Jul 2019)

  • Excavation of drainage channel
    (Mar/Jul 2019)

  • Drainage channel stabilized and functional
    (Mar/Jul 2019)

  • Staining of architectural treatment on abutment walls
    (Mar/Jul 2019)

  • Installation of guiderail along eastbound on-ramp to I-276
    (Mar/Jul 2019)

  • Grinding of concrete pavement
    (Mar/Jul 2019)

  • Installation of concrete median barrier and attenuator
    (Mar/Jul 2019)

  • Erection of monotube sign structure
    (Mar/Jul 2019)

  • Completed directional sign structure for eastbound/westbound on-ramps to I-276
    (Mar/Jul 2019)

  • Placement of stone layer for conversion of stormwater basin
    (Mar/Jul 2019)

  • Placement of amended soils for conversion of stormwater basin
    (Mar/Jul 2019)

  • Layering of amended soils, stone aggregate separated by geo-liner for converting stormwater basin 3B
    (Mar/Jul 2019)

  • Layering of amended soils, stone aggregate separated by geo-liner for converting stormwater basin 3A
    (Mar/Jul 2019)