PA Turnpike / I-95 Interchange Project

Section A1 - Bridge Replacement at Bensalem Interchange Ramps over Mainline

Project Description

The Section A1 project involves the replacement of the two existing bridges at the Bensalem (Route 1) Interchange with a single span bridge.  The footprint of the proposed bridge is being shifted east to accommodate the new staged ramp configuration for the future widening of the PA Turnpike. Additionally the existing Westbound on ramp will be realigned to improve the current traffic flow operations.

The construction for this project also includes:

  • Demolition of existing bridges over PA Turnpike mainline.
  • Building of mechanically stabilized earth (MSE) wall adjacent to eastbound PA Turnpike mainline off-ramp.
  • Construction of future eastbound PA Turnpike mainline off-ramp roadway.
  • Placement of concrete pavement via staged ramp reconstruction.
  • Upgrade of drainage measures and mast lighting installed throughout the Interchange.
  • Installation of a precast slab interlocking system located at the Interchange’s roadway approach.

Project Schedule

The Notice To Proceed was August 2016. The duration of the project is over two and half (2 ½) years with construction completing by May 2019.

Construction Status

September 2018

  • Placed Pre-Cast Pavement Slabs south of Ramp A/B bridge over I-276 at Bensalem Interchange over a weekend.
  • Graded and placed subbase north and south of Ramp A/B bridge over I-276 at Bensalem Interchange.
  • Continued forming and pouring concrete pavement north and south of Ramp A/B bridge over I-276 at Bensalem Interchange.
  • Installed manholes and drainage pipe between on-ramp to eastbound I-276 and on-ramp to westbound I-276.
  • Constructed Abutment No. 2 Approach Slab.

Image Gallery

  • Forming of proposed concrete pavement on the north side of the bridge
    (Sep 2018)

  • Installation of load transfer bars on the north side of the bridge
    (Sep 2018)

  • Completed concrete pavement on the north side of the bridge
    (Sep 2018)

  • Preparation for pouring concrete pavement adjacent to new roadway
    (Sep 2018)

  • Placement of concrete pavement south of bridge
    (Sep 2018)

  • Forming of median concrete pavement south of bridge
    (Sep 2018)

  • Grading for median concrete pavement south of bridge
    (Sep 2018)

  • Installation of drainage pipe between manhole and inlet
    (Sep 2018)

  • Removal of existing pavement in preparation to grading area for pre-cast pavement slabs
    (Sep 2018)

  • Placement and grading of cementitious sand for pre-cast pavement slabs
    (Sep 2018)

  • Drilling and inserting of dowel bars for pre-cast pavement slabs
    (Sep 2018)

  • Lifting of pre-cast pavement slabs into designated location
    (Sep 2018)

  • Leveling and interlocking of pre-cast pavement slab adjacent to existing concrete pavement
    (Sep 2018)